This bulletin was updated on September 16, 2026.
This is the latest on the Independent Electricity System Operator (IESO) Long Lead-Time Request for Proposals (LLT RFP). The LLT RFP aims to address growing demand in Ontario’s electricity sector by securing energy and capacity resources with longer lead times for project development.
Background
The IESO began engaging with stakeholders on the design of the LLT RFP in April 2025, following the issuance of the Long Lead-Time Request for Information (LLT RFI) in 2024. The IESO submitted the LLT RFI results and an LLT RFP design proposal to the Ministry of Energy and Mines (Ministry) on August 29, 2025. The IESO received a Directive from the Ministry on April 16, 2026, to formally launch the LLT RFP.
Eligibility
The LLT RFP is a reliability-based procurement intended to secure incremental energy and capacity from new-build resources with a lead time of five or more years that will contribute to system needs over a 40-year term, with a commercial operation date no later than May 1, 2035.
There will be no early in-service financial incentives. Commencing commercial operation under the LLT contract between May 2032 and May 2034 will require prior written IESO consent, which may be withheld by the IESO only due to deliverability constraints. Commencing commercial operation under the LLT contract after May 2034 will not require prior IESO consent. Connecting and operating the facility on a merchant basis prior to the commencement of the LLT contract is also permitted.
The LLT RFP will be administered as a single procurement window bifurcated into an energy stream (LLT(e)) of up to 1 TWh and a capacity stream (LLT(c)) of up to 800 MW.
The IESO has decided to include eligibility for separately metered expansions, including hydro redevelopments, in both the capacity and energy streams.
The energy stream will be open to new hydroelectric resources of at least 1 MW (i.e., reservoir hydro with storage capability, excluding pumped hydro).
The capacity stream will be open to new projects of at least 1 MW that use a long-duration (eight hours or more) energy storage (LDES) technology, including pumped hydro storage and compressed air energy storage (Class I) and liquid air energy storage and pumped thermal energy storage (Class II). The instantaneous maximum withdrawal capability of the facility must be at least the project’s monthly contract capacity. The IESO is introducing a bespoke independent engineering (IE) certification specific to Class II projects, verifying eligibility. Successful proponents may also be required to include public media events pertaining to the contracted facility in their quarterly progress reports leading up to commercial operation (which reports may be disclosed to the provincial government).
The IESO is proposing that LLT(c) and LLT(e) project proponents must have at least two team members with experience in each of planning, developing, financing, constructing and operating at least one “Qualifying Project” (i.e., nameplate capacity of at least 1 MW for LLT(e) and LLT(c) that achieved commercial operation in the last 15 years). The IESO has expanded the definition of “Qualifying Projects” for the LLT RFP beyond North America to include projects that have reached commercial operation in Japan, Australia and parts of Europe (U.K., Italy and France).
For the LLT(c) only, where a proponent is proposing a project utilizing a Class II LDES technology, they must also have at least two team members with experience in planning and developing a Same Technology Qualifying Project (i.e., one that uses the same storage technology, has a nameplate capacity of at least 1 MW and is expected to reach commercial operation in Canada, the U.S., the U.K., Italy, France, Australia, Germany or Japan on or before December 31, 2029). The IESO is also considering other reporting requirements.
The IESO has indicated that the LLT RFP will include a confidential Reserve Price (but will be shared with the Fairness Advisor ahead of the LLT RFP submission deadline) to ensure successful projects remain cost-effective. The Reserve Price will be calculated by the IESO, in part by reference to the results of the LT2 RFP (Window 1). The IESO will also not permit a second round of bid submissions where an initial bid exceeds the Reserve Price.
Rated Criteria
Rated criteria will be finalized by the Ministry in a directive to be issued shortly. For now,
- The IESO is proposing to award 1.5 rated criteria points for projects that can offer more than 10 hours of continuous energy, and to award 10 rated criteria for more than 12 hours of continuous energy (based on final test capacity check). These rated criteria would have a 5% impact on the overall evaluated LLT project proposal price.
- Rated criteria will also be offered for Indigenous community participation (i.e., up to 3 points can be obtained where the project involves Indigenous economic participation, and up to an additional 3 points where the project is located on traditional Indigenous territories). These rated criteria would have a 15% impact on the overall evaluated LLT project proposal price.
- For project sites on Indigenous lands and/or municipal project lands, a pre-engagement confirmation notice will be required. This notice must be delivered to the IESO at least 60 days before the date of the mandatory municipal and/or Indigenous community support confirmation. A municipal and/or Indigenous Community support resolution must also be provided as part of the final proposal submission for projects sited on applicable lands. Where the project is also sited on public lands managed by the Ministry of Natural Resources (MNR), the proponent must also include in its proposal MNR's written confirmation of the completeness of a Crown Land Site Report.
- No rated criteria points are available for siting projects outside of prime agricultural areas. For projects sited on prime agricultural lands, confirmation of completion of Agricultural Impact Assessment (AIA) requirements must be submitted to the IESO within 18 months of being awarded an LLT contract.
Contract Provisions
Regulation Service Equipment Installation
There is a new mandatory requirement for the installation of equipment to enable the provision of regulation services under a subsequent procurement or contract (i.e., regulation readiness).
Under the LLT(c), this requirement will apply to all transmission-connected facilities with a nameplate capacity of at least 40 MW. The minimum regulation capacity will be +/- 10 MW with an associated ramp rate of at least 50%. A verifying independent engineering certificate will be required. The IESO will have associated equipment testing and audit rights.
Tariff Impacts
The LLT will also include a provision that would permit suppliers to revise their proposal price based on post-proposal import tariffs, similar to the LT2 RFP. However, the IESO will have sole and absolute discretion to terminate the LLT contract based on the revised proposal price with no reimbursement of costs already incurred by the proponent.
Supply Chain Disclosure Plan
All proponents are required to include a confidential “Supply Chain Disclosure Plan” specifying the expected country of origin of goods and services (e.g. construction materials and labour costs) and the percentage of and explanation for when those goods and services are being sourced from suppliers outside Canada. Proponents must also include a line-item breakdown of how it intends to achieve the committed Canadian content percentage, if any.
While there is no minimum Canadian content level, proponents can elect to include such content for the purpose of obtaining additional incentives (i.e. if at least 60% domestic-sourced content or total project costs are achieved, then the IESO will apply a 1% reduction in the evaluated proposal price, with up to a 3% reduction for 100% domestic-sourced content). Liquidated damages, up to a maximum of C$5-million, could apply if the domestic-sourced content level is in fact unmet as at commercial operation.
Outages
For LLT(e) contracts, the IESO recommends that proponents incorporate planned outages in their imputed production factors to avoid availability non-performance charges. For capacity stream contracts, planned outages will similarly be considered as part of the calculation for availability non-performance charges and will be permitted over a single month or two months during a contract year.
The LLT will also permit mid-term extended outages of one or more units for up to a maximum of 12 months at the facility level. Such mid-term outages may be requested to take place beginning in the 11th contract year. During such mid-term outages, partial contract payments will be made for any units that continue to operate.
Environmental Attributes
The same environmental attributes regime as in the LT2 contracts (i.e., supplier benefits from revenue) is proposed for the first half of the 40-year contract. The IESO has confirmed that a revenue-sharing mechanism between the supplier and the IESO will apply for the last 20 years of the LLT contract term.
Reimbursement Reference Efficiency
The IESO has reduced the Reimbursement Reference Efficiency included in the calculation of the Regulatory Charge Credit for the LLT(c) from 75% to 60% to reflect lower expected round-trip efficiency.
Indexation
The IESO has indicated that escalation for the first contract year will be equal to the Indexed Fixed Capacity Payment (IFCP) or Indexed Fixed Price (IFP) multiplied by the Pre-COD Indexing Factor (based on Consumer Price Index (CPI)). For each subsequent contract year, 20% of the IFCP or IFP will be escalated by the index factor, which is based on the year-over-year changes to the CPI.
Next Steps
Final LLT RFPs, contracts and prescribed forms were posted on May 6, 2026, here.
The IESO has published a deliverability testing methodology document, which includes both pre-deliverability and deliverability considerations, incorporating certain results from the IESO's LT2 procurement outcomes. The IESO continues to offer deliverability consultation meetings with potential proponents for up to three connection arrangements / project sizes per proponent, until November 12, 2026.
Stakeholders are invited to submit written questions and comments to the IESO by July 10, 2026. The IESO has until August13, 2026, to issue any addenda to the final LLT RFP and/or contracts. LLT proposal submissions are due November 26, 2026 (with registration beginning September 23, 2026 up to and including October 6, 2026), and LLT contracts are to be awarded by May 25, 2027.
Our team is closely monitoring developments related to the LLT RFP and will provide updates as more details become available.
For more information, please contact the authors or any other member of our Energy Regulatory or Power groups.
Related Insights
Blakes and Blakes Business Class communications are intended for informational purposes only and do not constitute legal advice or an opinion on any issue. We would be pleased to provide additional details or advice about specific situations if desired.
For permission to republish this content, please contact the Blakes Client Relations & Marketing Department at [email protected].
© 2026 Blake, Cassels & Graydon LLP