Alberta Introduces Bill 42: New Legislative Framework for Data Centres

November 25, 2026

On November 18, 2026, the Government of Alberta introduced Bill 42, the Energy, Environment and Utilities Statutes Amendment Act, 2026 (Bill 42). Among other things, the omnibus bill would build out the regulatory framework for data centres. This bulletin discusses key changes proposed for data centres and related infrastructure.

Bringing Data Centres Under Alberta Utilities Commission Oversight

Bill 42 would bring data centres under the jurisdiction of the Alberta Utilities Commission (AUC) in certain cases, and amend the Hydro and Electric Energy Act to treat such data centres similarly to power plants and transmission lines for facility approval purposes. A “data centre” is broadly defined and encompasses one or more facilities that house computing equipment for data hosting and cloud computing, artificial intelligence and machine learning, and digital services and content delivery. It also includes facilities used for digital asset mining (capturing cryptocurrency mining operations). Cabinet may prescribe additional purposes by regulation.

Once in force, Bill 42 would prevent the construction or operation of a data centre above a prescribed demand threshold without AUC approval (the province has indicated 10 megawatts (MW) and larger). Facility approval would be subject to an AUC public-interest determination that would not consider the computing activities carried out by the data centre or how its data is used.

Bill 42 would also exempt designated data centre systems from AUC permit and licence requirements that ordinarily apply to transmission lines. The exemption extends to “a person who constructs or operates a transmission line as a part of a designated data centre system” on the system’s land or across a public highway dividing that land.

Under the current regime, each municipality has primary responsibility for approvals related to data centre development and the AUC has primary responsibility for the power plants that serve data centres. The province and the AUC have suggested that a benefit of bringing data centre regulation under the primary jurisdiction of the AUC is the consistent application of a single regulatory framework across the entire complex (i.e., power generation, wires and the data centre itself).

Data Centre Siting

Bill 42 would authorize Cabinet to make regulations prescribing how data centres are built and operated, including minimum setbacks from property lines, structures and particular types of land or land uses. While regulations have not been released, the province has stated that:

  • “Provincial minimum setbacks of 600 metres would be established for data centres 10 megawatts and larger” and alternative setbacks may be requested by municipalities; and

  • “Designated Industrial Zones, brownfield sites and existing power generation sites would be recognized to encourage development in areas already suited for major industrial projects.”

Echoing the province’s “agriculture first” policy for renewable energy project siting, Bill 42 also creates requirements for data centres built on high-quality agricultural land (a concept to be defined by regulation). An order of Cabinet would be required for such siting (in addition to AUC approval) until September 20, 2027, after which data centres on such land would remain subject to AUC oversight and any relevant regulations.

The New Data Centre System Designation

Bill 42 introduces a new exemption from the Electric Utilities Act (EUA) for a designated data centre system, covering "the portion of electric energy produced by a designated data centre system that is directly consumed by the designated data centre system." 

A “data centre system” is “an electric energy system that operates primarily for the use of a data centre” and consists of the data centre and the associated generating units, electric distribution system and transmission lines that connect the components of the data centre system, and energy storage facility.

Unless a project is designated by statute, the designation would be issued by the AUC upon application, provided certain preconditions are met. Among other things, the applicant must have the written consent of each owner of the data centre system, include the Alberta Electric System Operator (AESO) assessment of the system’s impact on grid reliability and adequacy, and demonstrate that:

  • The owners will bear the transmission costs and the system will support efficient exchange of electricity with the provincial grid and maintain or improve its reliability

  • At least one generator that forms part of the data centre system is located on the property where the data centre system is located that is intended to serve the data centre system

  • The maximum demand directly from the transmission system is equal to or greater than 75 MW or less than 75 MW if established by the AESO

The AUC will develop rules that govern such applications.

The data centre system designation exemption would be in addition to existing EUA exemptions, namely the self-supply exemption and the industrial system designation (ISD), giving data centre developers a purpose-built exemption path (the AUC recently denied an ISD associated with a data centre).

Cost Allocation

A key objective of Bill 42 is to ensure that the costs of a designated data centre system’s own wires do not fall to other ratepayers.

If the bill is passed, the AESO would not be able to recover the costs of a designated data centre system's transmission facilities through its rates, and the AUC could not permit the costs of transmission or distribution infrastructure within a designated data centre system to be included in any utility tariff. A transmission facility owner within a designated data centre system could file a tariff with the AUC, provided it is supported by a contract demonstrating cost recovery. The AESO would also be able to seek AUC approval to use a designated system’s transmission facilities to provide service to the grid on rates and terms set by the AUC.

Key Takeaways and Next Steps

Bill 42 includes grandfathering provisions that would exempt in-flight projects from certain requirements (including the requirement for AUC facility approval) depending on the stage of construction and operation, and would deem a person already constructing or operating a data centre when the relevant provisions come into force to hold an AUC approval. Data centre developers should assess whether their projects would qualify for grandfathering, with the understanding that certain details will be set by regulations that have yet to be released.

The bill has yet to be passed into law and many important details of the new regime are still to come; however, Bill 42 is the latest step by the province to encourage data centre investment while mitigating potential impacts to agricultural and residential landowners and ratepayers. For other data centre developments in Alberta, see our Blakes Bulletin: Connecting Data Centres to the Grid: Alberta's New Regulatory Framework and Emerging Trends in Ontario and Other Canadian Provinces.

Blakes will continue to monitor Bill 42 as it proceeds through the Legislative Assembly, including any amendments that might be made to the bill before it is passed. For more information, please contact the authors or any other member of our Power or Energy Regulatory groups.